This is a quotation provided to us for the renovation and extension of a 70 m2, two-story end of terrace house in Dublin, built in 1930. Solid concrete wall construction. Currently BER F.
The proposed ground floor extension is is 31 m2, and the proposed first floor extension is 20 m2. I'm posting the quotation here as a sanity check and to see if those more experienced than myself think it's reasonable, or if any items require some scrutiny.
The quotation is above what we are capable of paying I'd appreciate any advice on strategies to get this estimate considerably lower.
Construction of extension and renovation of existing house
Items not included
The proposed ground floor extension is is 31 m2, and the proposed first floor extension is 20 m2. I'm posting the quotation here as a sanity check and to see if those more experienced than myself think it's reasonable, or if any items require some scrutiny.
The quotation is above what we are capable of paying I'd appreciate any advice on strategies to get this estimate considerably lower.
Construction of extension and renovation of existing house
- Preliminaries, skips, site preparation, scaffolding, rubbish removal and site supervision 26000
- Demolition of existing rear structures and internal alterations 13700
- Foundations and ground works to new extensions 16000
- Insulated ground floors to extension 7400
- Blockwork to ground and first floor extensions 16000
- Structural steel and alterations to existing openings 14900
- New first floor structure 7400
- Pitched roof structure, coverings and connections to existing roof 23000
- Flat roofs, rooflight and aluminium cappings 13100
- Insulation and airtightness to new walls and roofs 9400
- External finishes to new extension and rainwater goods 7400
- Existing ground floor removal and insulated replacement floor preparation 9700
- Underfloor heating and standard screed - ground floor allowance 11400
- Air-to-water heat pump, cylinder, hot and cold water services and first floor radiators 27200
- Electrical alterations and installation to extension (90 electric points, white PVC finish) 14300
- Extractor fans and kitchen downdraft duct provision 3000
- New ceilings throughout, wall preparation and replastering 12600
- Bathroom construction and fit-out labour with recessed storage 10300
- Ground floor WC shower room and utility services 8000
- Internal doors, skirtings, architraves, window boards and consumer unit enclosure 8600
- Stair headroom alterations - provisional structural allowance 4000
- Attic floor and eaves insulation with approximately 12 m2 raised storage base 4600
- Remove gas fire, fireplace and hearth and prepare chimney for future stove 1700
- Flooring and tiling installation labour 5100
- Internal painting only (Dulux / Fleetwood paint) 9700
- External wall insulation 21000 (Front brick slips including canopy extension 5500)
- PC sum for external works - approximately 20 m2 external patio 4500
Items not included
- Windows
- Kitchen and fitted furniture
- Sanitaryware / tiles
- Floor finishes
- Solar panels
- MVHR
- No front garden works included