we got a sizeable landscaping job done in the past few weeks , involved laying a near 1700 sqr metre lawn , a 24 sqr metre patio ,planting a hedge row with 113 plants and two shrub beds with bark mulch and shale stone , we also erected a pergola
the landscaper does good work but he was a poor communicator throughout , he did not provide us with so much as a basic sketch outlining the pergola , we only discovered relatively late that he had something in mind which we did not expect , his idea was quite quirky to say the least but thankfully no work had been done before the penny dropped that we were not on the same page , had he presented a basic sketch , we could have easily edited it to meet our expectations
anyway , he sent me a revised bill today which added 550 euro on to the cost of the pergola , this job already cost 8700 euro and he sent us a quote last november which we didnt haggle over , i think its unreasonable to add lib on like that but perhaps im wrong and if some things get " lost in translation " , the right must be reserved to revise accordingly ?
he could just as easily have added on another grand from what I can see as there was no breakdown of extra costs , just sent me a text saying thats the " extra " for the Pergola
Im not in anyway hesitant to raise this with him but thought id ask the room for their thoughts ?
the landscaper does good work but he was a poor communicator throughout , he did not provide us with so much as a basic sketch outlining the pergola , we only discovered relatively late that he had something in mind which we did not expect , his idea was quite quirky to say the least but thankfully no work had been done before the penny dropped that we were not on the same page , had he presented a basic sketch , we could have easily edited it to meet our expectations
anyway , he sent me a revised bill today which added 550 euro on to the cost of the pergola , this job already cost 8700 euro and he sent us a quote last november which we didnt haggle over , i think its unreasonable to add lib on like that but perhaps im wrong and if some things get " lost in translation " , the right must be reserved to revise accordingly ?
he could just as easily have added on another grand from what I can see as there was no breakdown of extra costs , just sent me a text saying thats the " extra " for the Pergola
Im not in anyway hesitant to raise this with him but thought id ask the room for their thoughts ?