Guys,
Is it possible to have an engineer draw up one of these after a house has been built without he/she having seen the foundations being poured?
I started building my self build in Feb last year and am about ready to start fitting out the inside. I've completed the work so far using savings but now I need a mortgage to finish it..
I've been told I need a 6 point letter in order to secure a mortgage, but i never had an engineer present when the foundations were poured :-(
Surely I'm not the only person thats found themselves in this predicament. I've heard of projects where the engineer wasnt available on the day to witness the foundations being poured but they still signed off on the cert.
I have images of the whole build so far and have dug out the esb connection whole so the foundations are visible for examination/test.
Can anyone suggest a solution for me?
Cheers
dudeman
Is it possible to have an engineer draw up one of these after a house has been built without he/she having seen the foundations being poured?
I started building my self build in Feb last year and am about ready to start fitting out the inside. I've completed the work so far using savings but now I need a mortgage to finish it..
I've been told I need a 6 point letter in order to secure a mortgage, but i never had an engineer present when the foundations were poured :-(
Surely I'm not the only person thats found themselves in this predicament. I've heard of projects where the engineer wasnt available on the day to witness the foundations being poured but they still signed off on the cert.
I have images of the whole build so far and have dug out the esb connection whole so the foundations are visible for examination/test.
Can anyone suggest a solution for me?
Cheers
dudeman