Hi,
We signed a contract with a developer last February 2006 who was building a development of houses.
The development was to have been completed in February 2007.
He is now almost 5 weeks over the contract completion date and a general enquiry with the auctioneer says it will be at least July before he finishes
What are our options to enforce penalties and what do these penalties include.
We are currently renting a house at €1200 a month.
Can we claim this from the developer?
Or what exactly do penalties include?
Have we any other options?
IS a 28 day notice a good idea or are we better negotiating with the builders solicitor on say a price reduction?
Or have we any rights?
Any advice appreciated.
Thanks
I will be seeing my solicitor next week so I am just looking for general information.
Google has drawn a blank.
We signed a contract with a developer last February 2006 who was building a development of houses.
The development was to have been completed in February 2007.
He is now almost 5 weeks over the contract completion date and a general enquiry with the auctioneer says it will be at least July before he finishes
What are our options to enforce penalties and what do these penalties include.
We are currently renting a house at €1200 a month.
Can we claim this from the developer?
Or what exactly do penalties include?
Have we any other options?
IS a 28 day notice a good idea or are we better negotiating with the builders solicitor on say a price reduction?
Or have we any rights?
Any advice appreciated.
Thanks
I will be seeing my solicitor next week so I am just looking for general information.
Google has drawn a blank.