Builder dispute over unapproved variations

Rabbit

New Member
Messages
4
I'm looking for advice from anyone who has experienced a similar dispute with a building contractor, particularly regarding unapproved variations and failure to complete works.

I engaged a building contractor for a substantial renovation and two-storey extension to my home under a signed fixed-price contract in December 2025.

The contract provides that variations must be agreed in writing before works are undertaken, with adjustments to the contract price arising from approved variations.

Unfortunately, the project has been beset by delays, additional costs and repeated missed completion dates. The original completion date was April 2026, and the house remains unfinished in late October.

The main dispute

The builder is now seeking substantial additional payments for works that were never priced, approved or agreed as variations.

The builder proceeded with these works without following the contractual variation process and is now attempting to recover the costs retrospectively.

I have accepted a number of other legitimate variations, including additional works that were properly discussed and priced. I am not refusing to pay for genuinely agreed additional works.

Completion issues

The builder has repeatedly missed agreed completion dates, including a revised date of 1 October 2026.

There are still outstanding plumbing, carpentry, electrical and finishing works, along with defects and snagging.

Despite the outstanding works, the builder has requested further advance payments and continues to pursue payment for the disputed variations.

I have already paid substantial sums under the contract, including an additional €15,000 advance in September to assist the builder with cash flow.

Legal advice

I have consulted a solicitor, who has advised that the builder does not have a contractual entitlement to payment for the disputed variations on the facts presented.

I have also been advised to issue a formal notice requiring completion within 14 days and, if the builder fails to comply, to consider terminating the contract in accordance with its terms and engaging another contractor to finish the project.

My preference throughout has been to have the original builder complete the house, settle the legitimate final account and move on. However, confidence in the contractor has been seriously undermined.

My questions are:

Has anyone successfully disputed retrospective charges for building works that were never priced or approved under a written contract?

Has anyone terminated a building contract due to failure to complete, and subsequently engaged another contractor?

What practical or financial difficulties did you encounter following termination?

If the builder pursues payment through a solicitor or debt collection process, how was the dispute ultimately resolved?

I appreciate that every contract and dispute is different, and I have already obtained legal advice. I'm particularly interested in hearing about people's actual experiences and how these situations were resolved.

At this stage, I simply want my house completed without being forced to pay substantial additional charges that I never agreed to.
 
Last edited:
Two questions:
Do you have an Architect who is involved in the construction phase of the project?
Do you have a Quantity Surveyor?
 
Last edited:
Yes, we have an architect who has been involved throughout the project, including inspections during the construction phase.

We also had a Quantity Surveyor who prepared the original Bill of Quantities and was involved in the payment applications. However, his relationship with the builder has since broken down, and he is no longer involved.

We are currently obtaining legal advice regarding the builder's failure to complete the works and his claims for additional payments for variations that were never agreed or approved in writing, as required under our contract.

We're considering engaging an independent QS to review the final account and disputed variations.
 
Yes, we have an architect who has been involved throughout the project, including inspections during the construction phase.
That's good. I'm near the end of a large refurbishment project. My builder refused to recommend a QS as he said the client has to have the relationship with the QS, not the builder. He also insisted that the Architect be involved at every stage. We are within 2% of budget.

I strongly recommend that you copy your architect in as much correspondence as possible. They will certainly have more experience and expertise in this are than you.
 
I'm a little late to the party but you've said you have obtained legal advice so why are you asking for advice here and indeed on Boards.ie where you were given lots of it? Legal advice will always trump anything that's posted by random strangers on an online discussion forum.
 
Sometimes things happen on site and variations must happen. It’s very tricky. The QS is probably the best professional to consider if additional changes were necessary and properly priced, in consultation with the architect. Has your QS or architect expressed an opinion. We too have just finished an 15 month project.
 
@nutty nut my main question is

Has anyone successfully disputed retrospective charges for building works that were never priced or approved under a written contract?

I'm just trying to gather as much information as possible and sometimes it's worth asking for details from anyone who may have gone through a similar situation
 
@DeeKie we plan on getting an independent QS to review the original tender BoQ, the works completed to date to establish what the builder is genuinely owed outside of the disputed amounts that were never approved as per the contract
 