Seems my knowledge may be out-of-date actually
@Leo. Back when I last looked at it (2021/2022 maybe) the wording from the SEAI appeared to specifically prohibit a transfer setup if you were using the grant, or that was certainly how most installers seemed to interpret it -
....Part B of the building regulations and I.S.10101, all domestic PV installations installed under this Scheme must:
• Provide an automatic (i.e., automatically operated by disconnection of the main AC supply to the building) shunt (or interlocked) isolation of the circuit (whether AC or DC, and two pole) from the solar PV modules into the building, as close to the solar PV modules as possible, and a maximum of 1.5m internally from the point of cable entry to the building. • Where the circuit from the solar PV modules does not enter the building, this point of automatic isolation must be within 1.5m of the solar PV modules. • For ground mounted system the shunt (automatic isolator) must be within 1.5m of the solar PV modules.
• This system of isolation shall automatically isolate the circuit from solar PV modules when the AC supply is disconnected to the building, i.e., a shunt or interlocked isolation function.
• ‘Shunt’ or ‘interlocked’ isolation of the DC circuit is the only acceptable manner of meeting the Building Regulation TGD B – Fire Safety (2017) for the purposes of this Scheme.
• For the avoidance of doubt the disconnection of the circuit from the solar PV modules must be automatic and operated by removal of AC supply to the building and must not be operated by means of a dedicated switch, pushbutton, ‘fireman’s switch’ or other manner.
• For the avoidance of doubt an isolation of the supply from the PV modules is required in ALL cases, whether micro-inverters, DC optimised inverters, where the inverter is within 1.5m of cable entry or any other configuration is used.
Now SEAI have a page dedicated to powering your home from solar/battery during a power outage which is great -
https://www.seai.ie/blog/solar-panels-power-cut