Irish Rail wanted to end contract last year for delayed IT project company
TDs to hear from State-owned rail company about €50m write-down on system to manage movement of trains
Irish Rail chief executive Mary Considine is expected to tell the committee on Wednesday that six years after a contract was signed and two years after the original date for its commissioning, Indra “still does not have a developed product that is fit for deployment on the network”.
‘National scandal’: Committee seeks urgent meetings on €50m write-off of Irish Rail IT project
‘€50 million has now been written off by Irish Rail on this project and there just simply has to be accountability.’
Under the initial proposals, the system was targeted to be commissioned in 2024, with a target cost of €19.5 million.
As of the most recent update provided to the Public Accounts Committee, over €31.5 million had been spent on the IT system, with not even the first phase completed.
I've been reading articles about this for a while.
In a career in IT I've observed or been involved in projects that went off the rails (sorry for the pun) but to hear Irish Rail already paid so much for a system in which the first phase hasn't even been delivered is shocking. This suggests really poor contract management and poor vendor control. The vendor here is the Spanish Indra group with whom I am not familiar.
I'm curious if anyone on this forum has any deeper insight into what happened here.