Am thinking of proposing the following to my contractor for a builders finish:
- Once the foundations are laid. 10%
- The roof level is completed, slates are on and house is weather tight. 25%
- The plastering is complete. 25%
- The house is finished as specified. 25%
15% of the payment will be withheld until house snag list has been rectified.
Any comments? Is this too simplistic. What have others done?
Mac