B Birroc Registered User Messages 278 8 Jul 2008 #1 Hi, When is considered half way on a direct labour build ? Windows are in and we are at external plastering stage. Not too many hold-ups so far, tradesmen seem quite eager to work. Just curious how long is left. I am not really stressed yet even though I feel the worst is yet to come. Great experience so far.
Hi, When is considered half way on a direct labour build ? Windows are in and we are at external plastering stage. Not too many hold-ups so far, tradesmen seem quite eager to work. Just curious how long is left. I am not really stressed yet even though I feel the worst is yet to come. Great experience so far.
D Dreamhouse Registered User Messages 26 11 Jul 2008 #2 If sewerage, water suply, studs are done, than it's 25-35% depends on finishes. 50% - when 1st fix on electrics, plumbing done and place skimmed.
If sewerage, water suply, studs are done, than it's 25-35% depends on finishes. 50% - when 1st fix on electrics, plumbing done and place skimmed.