After you get the plastered shell back from the builder the skys the limit as far as what you spend to fit out a house but here’s my figures. Once you get the main shell done and have 20 to 40k left you will be fine. If you find that you run short you just have to have rooms unfinished etc None of this stuff would be top of the range but no tile style or flat pack rubbish either
Note how quick you can spend 30,000
Main bathroom
Tiling and tiler 1200
Suite should be included in the 160,000
Ensuite 600
As above suite should be included in the 160,000
Timber ground floors solid in public areas (hall, dining and living) allow €50 min per sq yard. 3000
Laminate floors bedrooms DIY allow 30 sq metre 1500
Wardrobes allow 800 each room
Fireplace 1500
Kitchen 10,000
Kitchen tiling 1500
Furniture 4,000
Landscaping and fencing 5,000 ?